INTFC_TEAM_GEN(SQL Table) |
Index Back |
---|---|
Third-Party Resource StagingThird-Party Resource Staging table for loading Project Team and/or Activity Team from a third-party system. |
# | PeopleSoft Field Name | PeopleSoft Field Type | Database Column Type | Description |
---|---|---|---|---|
1 | INTFC_ID | Number(8,0) | INTEGER NOT NULL | Interface ID |
2 | INTFC_LINE_NUM | Number(8,0) | INTEGER NOT NULL | Interface Line Number |
3 | BUSINESS_UNIT | Character(5) | VARCHAR2(5) NOT NULL |
Business Unit
Default Value: OPR_DEF_TBL_PC.BUSINESS_UNIT Prompt Table: SP_BU_PC_NONVW |
4 | PROJECT_ID | Character(15) | VARCHAR2(15) NOT NULL |
Project Id ChartField
Default Value: OPR_DEF_TBL_PC.PROJECT_ID Prompt Table: SP_PROJ_NONVW |
5 | ACTIVITY_ID | Character(15) | VARCHAR2(15) NOT NULL |
Activity ID
Prompt Table: PROJ_ACTIVITY |
6 | TEAM_MEMBER_CLASS | Character(1) | VARCHAR2(1) NOT NULL |
05/26/2004 - FS
Translate Value "O" added.
A=Asset L=Labor M=Material O=Other Default Value: L |
7 | TEAM_MEMBER_IND | Character(1) | VARCHAR2(1) NOT NULL |
Team Member Indicator
E=Employee G=Generic Resource N=Not Applicable Default Value: E |
8 | TEAM_MEMBER | Character(30) | VARCHAR2(30) NOT NULL |
Team Member
Prompt Table: %EDIT_ID_NUM |
9 | PROCESS_INSTANCE | Number(10,0) | DECIMAL(10) NOT NULL | Process Instance |
10 | PLAN_STARTDT | Date(10) | DATE |
Planned Start Date
Default Value: PROJECT.START_DT |
11 | PLAN_ENDDT | Date(10) | DATE |
Planned End Date
Default Value: PROJECT.END_DT |
12 | PROJ_ROLE | Character(15) | VARCHAR2(15) NOT NULL |
Project Role
Default Value: BUS_UNIT_OPT_PC.PC_DEFAULT_ROLE Prompt Table: PROJ_ROLE |
13 | BUSINESS_UNIT_AM | Character(5) | VARCHAR2(5) NOT NULL | AM Business Unit |
14 | ASSET_TYPE | Character(3) | VARCHAR2(3) NOT NULL |
Asset Type
010=IT Hardware 020=IT Software 040=Equipment 050=Property 060=Fleet 070=Machinery 080=Furniture 090=Facility 100=Intangible 200=Asset Retirement Obligations 999=Other |
15 | ASSET_SUBTYPE | Character(15) | VARCHAR2(15) NOT NULL |
Asset Subtype
Prompt Table: AM_SUBTYPE |
16 | MODEL | Character(30) | VARCHAR2(30) NOT NULL |
Model
Prompt Table: MFG_MODEL_VW |
17 | MFG_ID | Character(50) | VARCHAR2(50) NOT NULL |
Manufacturer ID
Prompt Table: MANUFACTURER |
18 | AVAIL_UNITS | Number(6,0) | INTEGER NOT NULL | Availability Units |
19 | UNIT_OF_MEASURE | Character(3) | VARCHAR2(3) NOT NULL |
Used on an approval rule set.
MHR=Muti Hourly PER=Percentage SQF=Square Footage Default Value: OPR_DEF_TBL_PC.UNIT_OF_MEASURE Prompt Table: UNITS_TBL |
20 | PGM_RATE_TYPE | Character(1) | VARCHAR2(1) NOT NULL |
06/15/2004 FS - Changed eff. dates to 1/1/1900 from 1/1/2000
C=Override Rate E=Employee Rate J=Jobcode Rate R=Project Role Rate X=Custom Rate Default Value: C |
21 | COST_RATE | Number(27,3) | DECIMAL(26,3) NOT NULL | Cost Rate |
22 | CURRENCY_CD | Character(3) | VARCHAR2(3) NOT NULL |
Currency Code
Default Value: BUS_UNIT_TBL_PC.CURRENCY_CD Prompt Table: CURRENCY_CD_TBL |
23 | BILL_RATE_TYPE_1 | Character(1) | VARCHAR2(1) NOT NULL |
06/03/2004 - PR_FS_B005 Estimanting Labor PRL/ARL Changes
C=Override Rate E=Employee Rate J=Jobcode Rate R=Project Role Rate X=Custom Rate Default Value: C |
24 | BILL_RATE | Number(27,3) | DECIMAL(26,3) NOT NULL | Billing Rate |
25 | BILL_CURRENCY_CD | Character(3) | VARCHAR2(3) NOT NULL |
Bill Currency Code
Default Value: BUS_UNIT_TBL_PC.CURRENCY_CD Prompt Table: CURRENCY_CD_TBL |
26 | ASSGND_WORK | Signed Number(16,2) | DECIMAL(14,2) NOT NULL |
Assigned Work
Default Value: 0 |
27 | BASELINE_WORK | Signed Number(16,2) | DECIMAL(14,2) NOT NULL | Baseline Work |
28 | SOURCE_FLAG | Character(1) | VARCHAR2(1) NOT NULL |
Team member created from
6=Primavera P6 G=Proposal Management M=MSP P=Projects online R=Resource Management |
29 | INTFC_STATUS | Character(3) | VARCHAR2(3) NOT NULL |
Interface Status
CON=Consolidated DON=Mass Changes Generated ERR=Error NEW=Mass Changes Not Generated REP=Replaced by Other Records (AP) UNI=Unitized Default Value: NEW |
30 | LOAD_STATUS | Character(3) | VARCHAR2(3) NOT NULL |
/* -> JMZ. PSOFT. 11-OCT-2002 */
New Status were added : HLD and INP for Asset Management.
/* <- JMZ. PSOFT. 11-OCT-2002 */
CON=Consolidated DON=Loaded ERR=Errored EXC=Excluded HLD=On Hold INP=In Process NEW=Pending PGI=PO Grp Incomplete REP=Replaced UNI=Unitized Default Value: NEW |
31 | ERR_REASON | Character(3) | VARCHAR2(3) NOT NULL |
Reason code for error
ACT=Activity Error DUP=Duplicate EDT=Invalid Field Value PRJ=Project Error REQ=Required Field Missing SUM=Resource at Summary Activity |
32 | PC_DURATION | Number(11,2) | DECIMAL(10,2) NOT NULL | Duration |
33 | P6_MERGED_ASSIGNMT | Character(1) | VARCHAR2(1) NOT NULL |
An indicator that tells whether a resource assignment (activity team member) originated from a merging of multiple P6 assignments.
N=Not Merged Y=Merged Y/N Table Edit Default Value: N |
34 | PROJECT_OBJECTID | Number(10,0) | DECIMAL(10) NOT NULL | A unique ID that is the Project key to a corresponding table in an external system such as Primavera. |
35 | ACTIVITY_OBJECTID | Number(10,0) | DECIMAL(10) NOT NULL | A unique ID that is the Activity key to a corresponding table in an external system such as Primavera. |
36 | RESASSIGN_OBJECTID | Number(10,0) | DECIMAL(10) NOT NULL | A unique ID that is the Resource Assignment key to a corresponding table in an external system such as Primavera. |
37 | P6_TSKRS_GUID | Character(36) | VARCHAR2(36) NOT NULL | P6 ResourceAssignment GUID |