PC_ETC_DATE_VW(SQL View) |
Index Back |
---|---|
View of ETC Date by ProjectView of Forecasted Estimate to Complete Date for each Project. Projects with a Forecasting level other than 'A' (activity) will be excluded. We do not report on projects that are only forecasted at the 'P' (project) level. |
SELECT A.BUSINESS_UNIT_PC , A.PROJECT_ID , D.PROJECT_TYPE , D.END_DT , MAX(A.COMPLETION_DATE) FROM PS_FC_TIME_DTL A , PS_FC_TIME_HDR B , PS_PC_HORIZON_VW C , PS_PROJECT D WHERE A.EMPLID = B.EMPLID AND A.BEGIN_DT = B.BEGIN_DT AND B.BUSINESS_UNIT_GL = C.BUSINESS_UNIT_GL AND B.BEGIN_DT = C.BEGIN_DT AND A.BUSINESS_UNIT_PC = D.BUSINESS_UNIT AND A.PROJECT_ID = D.PROJECT_ID AND D.FORECAST_LEVEL = 'A' GROUP BY A.BUSINESS_UNIT_PC, A.PROJECT_ID, D.PROJECT_TYPE, D.END_DT |
# | PeopleSoft Field Name | PeopleSoft Field Type | Database Column Type | Description |
---|---|---|---|---|
1 | BUSINESS_UNIT | Character(5) | VARCHAR2(5) NOT NULL | Business Unit |
2 | PROJECT_ID | Character(15) | VARCHAR2(15) NOT NULL | Project Id ChartField |
3 | PROJECT_TYPE | Character(5) | VARCHAR2(5) NOT NULL |
Project Type
A=Activity G=Grant H=Phase P=Project S=Segment |
4 | END_DT | Date(10) | DATE | End Date |
5 | COMPLETION_DATE | Date(10) | DATE | Completion Date |