PC_ETC_TAO(SQL Table) |
Index Back |
---|---|
Record to capture ETC dataThis is a record that will capture estimate to complete data for the Estimate to Complete analytic. |
# | PeopleSoft Field Name | PeopleSoft Field Type | Database Column Type | Description |
---|---|---|---|---|
1 | OPRID | Character(30) | VARCHAR2(30) NOT NULL | A user's ID (see PSOPRDEFN). |
2 | BUSINESS_UNIT | Character(5) | VARCHAR2(5) NOT NULL | Business Unit |
3 | PROJECT_ID | Character(15) | VARCHAR2(15) NOT NULL | Project Id ChartField |
4 | ACTIVITY_ID | Character(15) | VARCHAR2(15) NOT NULL | Activity ID |
5 | PROJECT_TYPE | Character(5) | VARCHAR2(5) NOT NULL |
Project Type
A=Activity G=Grant H=Phase P=Project S=Segment |
6 | PROJECT_STATUS | Character(1) | VARCHAR2(1) NOT NULL |
Project Status
B=Budgeted C=Closed H=Hold O=Open P=Proposed |
7 | PC_BUDGET_HRS | Signed Number(16,2) | DECIMAL(14,2) NOT NULL | Budget Hours |
8 | PC_ACTUAL_HRS | Signed Number(16,2) | DECIMAL(14,2) NOT NULL | Actual Hours |
9 | PC_ETC_HRS | Signed Number(16,2) | DECIMAL(14,2) NOT NULL | Forecast to Complete Hours |
10 | PC_PROJECTED_HRS | Signed Number(16,2) | DECIMAL(14,2) NOT NULL | Actual Hours |
11 | PC_NUM_TEAM_MEMS | Number(5,0) | INTEGER NOT NULL | Number of Team Members |
12 | END_DT | Date(10) | DATE | End Date |
13 | COMPLETION_DATE | Date(10) | DATE | Completion Date |
14 | VAR_PCT | Signed Number(24,0) | DECIMAL(23) NOT NULL | Variance Percentage |
15 | PC_VAR_DAYS | Signed Number(6,0) | DECIMAL(5) NOT NULL | Variance (Days) |