PC_MSP2_ACTALVW

(SQL View)
Index Back

View of PS_PROJ_ACTIVITY

FROM PS_PROJ_ACTIVITY A

SELECT A.BUSINESS_UNIT , A.PROJECT_ID , A.ACTIVITY_ID , A.DESCR , A.ACTIVITY_TYPE , A.WBS_ID , A.EFF_STATUS , A.START_DT , A.END_DT , A.EARLY_START_DT , A.EARLY_FINISH_DT , A.LATE_START_DT , A.LATE_FINISH_DT , A.ACTUAL_START_DT , A.ACTUAL_FINISH_DT , A.BASELINE_START_DT , A.BASELINE_FINISH_DT , A.PERCENT_COMPLETE , A.PC_MILESTONE_FLG , A.PC_SCH_FIELD1 , A.PC_SCH_FIELD2 , A.ACTIVITY_USER1 , A.ACTIVITY_USER2 , A.ACTIVITY_USER3 , A.ACTIVITY_USER4 , A.ACTIVITY_USER5 , A.SUMMARY_ACT , A.PC_DURATION , A.ASSGND_WORK , A.ACTUAL_WORK , A.REMAINING_WORK , A.BASELINE_WORK , A.COST , A.PC_MSP_UNIQUE_ID , A.LEVEL_NUM , A.ROW_NUMBER_5 , A.DEADLINE_DT , A.CONSTRAINT_TYPE , A.CONSTRAINT_DT FROM PS_PROJ_ACTIVITY A

# PeopleSoft Field Name PeopleSoft Field Type Database Column Type Description
1 BUSINESS_UNIT Character(5) VARCHAR2(5) NOT NULL Business Unit
2 PROJECT_ID Character(15) VARCHAR2(15) NOT NULL Project Id ChartField
3 ACTIVITY_ID Character(15) VARCHAR2(15) NOT NULL Activity ID
4 DESCR Character(30) VARCHAR2(30) NOT NULL Description
5 ACTIVITY_TYPE Character(5) VARCHAR2(5) NOT NULL Activity Type
A=Activity Type
E=Entry Type
G=Group Type/Origin
O=Activity Type/Origin
R=Entry Type/Reason
6 WBS_ID Character(100) VARCHAR2(100) NOT NULL WBS ID
7 EFF_STATUS Character(1) VARCHAR2(1) NOT NULL Effective Status
A=Active
I=Inactive
8 START_DT Date(10) DATE Start Date
9 END_DT Date(10) DATE End Date
10 EARLY_START_DT Date(10) DATE Early Start Date
11 EARLY_FINISH_DT Date(10) DATE Early Finish Date
12 LATE_START_DT Date(10) DATE Late Start Date
13 LATE_FINISH_DT Date(10) DATE Late Finish Date
14 ACTUAL_START_DT Date(10) DATE Actual Start Date
15 ACTUAL_FINISH_DT Date(10) DATE Actual Finish Date
16 BASELINE_START_DT Date(10) DATE Baseline Start Date
17 BASELINE_FINISH_DT Date(10) DATE Baseline Finish Date
18 PERCENT_COMPLETE Number(6,2) DECIMAL(5,2) NOT NULL % Complete
19 PC_MILESTONE_FLG Character(1) VARCHAR2(1) NOT NULL Milestone Activity
N=No
Y=Yes
20 PC_SCH_FIELD1 Character(40) VARCHAR2(40) NOT NULL Generic field used for Projects Third Party Schedule Integration.
21 PC_SCH_FIELD2 Character(40) VARCHAR2(40) NOT NULL Generic field used for Projects Third Party Schedule Integration.
22 ACTIVITY_USER1 Character(10) VARCHAR2(10) NOT NULL User 1
23 ACTIVITY_USER2 Character(10) VARCHAR2(10) NOT NULL User 2
24 ACTIVITY_USER3 Character(10) VARCHAR2(10) NOT NULL User 3
25 ACTIVITY_USER4 Character(10) VARCHAR2(10) NOT NULL User 4
26 ACTIVITY_USER5 Character(10) VARCHAR2(10) NOT NULL User 5
27 SUMMARY_ACT Character(1) VARCHAR2(1) NOT NULL Flag to indicate whether an activity is summary or detail.
N=Detail Activity
Y=Summary Activity
28 PC_DURATION Number(11,2) DECIMAL(10,2) NOT NULL Duration
29 ASSGND_WORK Signed Number(16,2) DECIMAL(14,2) NOT NULL Assigned Work
30 ACTUAL_WORK Signed Number(16,2) DECIMAL(14,2) NOT NULL Actual Work
31 REMAINING_WORK Signed Number(16,2) DECIMAL(14,2) NOT NULL New Remaining work in hours
32 BASELINE_WORK Signed Number(16,2) DECIMAL(14,2) NOT NULL Baseline Work
33 COST Signed Number(28,3) DECIMAL(26,3) NOT NULL Total Cost
34 PC_MSP_UNIQUE_ID Character(22) VARCHAR2(22) NOT NULL Proj Act Unique ID
35 LEVEL_NUM Number(3,0) SMALLINT NOT NULL Level
36 ROW_NUMBER_5 Number(5,0) INTEGER NOT NULL Row Number
37 DEADLINE_DT Date(10) DATE Deadline Date
38 CONSTRAINT_TYPE Character(4) VARCHAR2(4) NOT NULL Constraint Type
ALAP=As Late As Possible
ASAP=As Soon As Possible
ENET=End No Earlier Than
ENLT=End No Later Than
MEO=Must End On
MSO=Must Start On
SNET=Start No Earlier Than
SNLT=Start No Later Than
39 CONSTRAINT_DT Date(10) DATE Constraint Date