PC_PROJHEALTH(SQL Table) |
Index Back |
---|---|
Project Level HealthProject Level Health |
# | PeopleSoft Field Name | PeopleSoft Field Type | Database Column Type | Description |
---|---|---|---|---|
1 | BUSINESS_UNIT | Character(5) | VARCHAR2(5) NOT NULL | Business Unit |
2 | PROJECT_ID | Character(15) | VARCHAR2(15) NOT NULL | Project Id ChartField |
3 | PC_HEALTH_TYPE | Character(1) | VARCHAR2(1) NOT NULL |
Project Health Type
B=Budget I=Issues K=Risks P=Project R=Resources S=Schedule U=User Defined |
4 | PC_HEALTH_CALC | Character(1) | VARCHAR2(1) NOT NULL |
A flag that identifies whether Project Health will be calculated or entered manually.
C=Calculated M=Manual Entry |
5 | PC_HEALTH | Character(1) | VARCHAR2(1) NOT NULL |
Calculated based on user-defined criteria, this field shows the overall health of a project.
F=Fair G=Good P=Poor |
6 | PC_HEALTH_DTTM | DateTime(26) | TIMESTAMP | The datetime stamp of when Project Health was either calculated or manually entered. |
7 | ACT_OVRDUE_PCT | Number(6,2) | DECIMAL(5,2) NOT NULL | Activity Overdue Percent |
8 | START_DT | Date(10) | DATE | Start Date |
9 | END_DT | Date(10) | DATE | End Date |
10 | PC_DURATION | Number(11,2) | DECIMAL(10,2) NOT NULL | Duration |
11 | PERCENT_COMPLETE | Number(6,2) | DECIMAL(5,2) NOT NULL | % Complete |
12 | PC_COST_VARIANCE | Signed Number(28,3) | DECIMAL(26,3) NOT NULL | Cost Variance is the difference between actual costs and budgeted costs. |
13 | VARIANCE_PERCENT | Signed Number(16,2) | DECIMAL(14,2) NOT NULL | Variance Percentage |
14 | PC_BUDGET_TOTAL | Signed Number(28,3) | DECIMAL(26,3) NOT NULL | Project Budgeting: Budget Plan Total |
15 | PC_COST_AMOUNT | Signed Number(28,3) | DECIMAL(26,3) NOT NULL | Total cost for a project. |
16 | OVRLOAD_PCT | Number(6,2) | DECIMAL(5,2) NOT NULL | A field that stores Overload Percent |
17 | TOT_RESOURCE | Number(8,0) | INTEGER NOT NULL | Total Number Of Resources |
18 | TOT_OVRLD_RES | Number(8,0) | INTEGER NOT NULL | Total Overloaded Resources |
19 | PC_HIGH_ISS_PCT | Number(6,2) | DECIMAL(5,2) NOT NULL | Project High Issues Percent |
20 | PC_ISS_HIGH | Number(4,0) | SMALLINT NOT NULL | Number of High Issues |
21 | PC_ISS_MEDIUM | Number(4,0) | SMALLINT NOT NULL | Number of Medium Issues |
22 | PC_ISS_LOW | Number(4,0) | SMALLINT NOT NULL | Number of Low Issues |
23 | RISK_NO_PLAN_PCT | Number(6,2) | DECIMAL(5,2) NOT NULL | Project High Issues Percent |
24 | RISKS_NO_PLAN | Number(8,0) | INTEGER NOT NULL | Risks without Action Plan |
25 | RISKS_WITH_PLAN | Number(8,0) | INTEGER NOT NULL | Risks with Action Plan |
26 | TOTAL_RISKS | Number(8,0) | INTEGER NOT NULL | Total Risks |