RUN_CNTL_PC_MSP

(SQL Table)
Index Back

MSP Integration

Run control for MSP Integration

# PeopleSoft Field Name PeopleSoft Field Type Database Column Type Description
1 OPRID Character(30) VARCHAR2(30) NOT NULL A user's ID (see PSOPRDEFN).

Prompt Table: PSOPRDEFN_SRCH

2 RUN_CNTL_ID Character(30) VARCHAR2(30) NOT NULL Run Control ID
3 BUSINESS_UNIT Character(5) VARCHAR2(5) NOT NULL Business Unit

Default Value: OPR_DEF_TBL_PC.BUSINESS_UNIT

Prompt Table: SP_BU_PC_NONVW

4 PROJECT_ID Character(15) VARCHAR2(15) NOT NULL Project Id ChartField

Default Value: NEXT

5 PC_SYNC_DIR Character(3) VARCHAR2(3) NOT NULL Sync direction for MSP Integration. CMS = Copy to Microsoft CPS = Copy to PeopleSoft UMS = Update Microsoft UPS = Upgrade PeopleSoft UPR = Get Update from Project Resource List (PRL)
CMS=Copy Project to Microsoft
CPS=Copy Project to PeopleSoft
UMS=Update Project in Microsoft
UPR=Project Resource List Update
UPS=Update Project in PeopleSoft
6 PROJ_DESCR Character(30) VARCHAR2(30) NOT NULL Project ID Description
7 INTEGRATION_TMPL Character(15) VARCHAR2(15) NOT NULL Integration

Prompt Table: PC_INT_TMPL

8 PROJECT_TYPE Character(5) VARCHAR2(5) NOT NULL Project Type
A=Activity
G=Grant
H=Phase
P=Project
S=Segment

Prompt Table: PROJ_TYPE_TBL

9 PROJECT_STATUS Character(1) VARCHAR2(1) NOT NULL Project Status
B=Budgeted
C=Closed
H=Hold
O=Open
P=Proposed

Prompt Table: PROJ_STATUS_TBL
Set Control Field: SETID

10 EFF_STATUS Character(1) VARCHAR2(1) NOT NULL Effective Status
A=Active
I=Inactive
11 TREE_NAME Character(18) VARCHAR2(18) NOT NULL Tree Name

Prompt Table: PC_TREESTRCT_VW

12 TREE_EFFDT Date(10) DATE Effective date of the Tree

Prompt Table: PC_TREE_EFDT_VW

13 PARENT_NODE Character(20) VARCHAR2(20) NOT NULL Parent Tree Node

Prompt Table: PC_TREE_NODE_VW

14 ATTACHSYSFILENAME Character(128) VARCHAR2(128) NOT NULL Unique Sys Filename
15 ATTACHUSERFILE Character(64) VARCHAR2(64) NOT NULL Attached File
16 CHARGING_LEVEL Character(1) VARCHAR2(1) NOT NULL Project Charging Level - identifies which level of the WBS activities are available for charging. 'D' indicates the detail level, which means all detail activities are available for charging. '1' indicates level 1 of the WBS is available for charging. '2' indicates level 2 of the WBS is available for charging. '3' indicates level 3 of the WBS is available for charging.
1=Costing Level 1
2=Costing Level 2
3=Costing Level 3
D=Detail
17 CHARGING_LEVEL_TR Character(1) VARCHAR2(1) NOT NULL Time Report Charging Level - identifies which level of the WBS activities are available for charging on time reports enter in Expenses. 'D' indicates the detail level, which means all detail activities are available for charging. '1' indicates level 1 of the WBS is available for charging. '2' indicates level 2 of the WBS is available for charging. '3' indicates level 3 of the WBS is available for charging.
1=Costing Level 1
2=Costing Level 2
3=Costing Level 3
D=Detail